Sustainability & Responsibility

left arrow

We are focusing on the UN’s #7 Sustainability Development Goal: Affordable and Clean Energy and we invite you to pledge your house to the cause.

left arrow

We support PMI’s 2022 Hours for Impact initiative where we have committed to assisting local organizations in executing their projects

Our team also volunteers to help organize events in their technical and personal circles, most recently the PMI’s 2022 Revelations Symposium.

We are always looking for additional causes to support, from river and lake cleanups to teaching and volunteer opportunities to many others.

Feel free to reach out at any time.

GHG Emissions

Limoges - Replacing dam at Lac L'Heureux - Project and Construction Management

Description de projet

Terrassement Limoges et Fils mandated Equinox Construction Services (ECS) to manage the replacement of the Lac L'Heureux Dam. The work included in the project was the design and construction of a cofferdam, the complete removal of the existing work, the construction of a reinforced concrete structure with three sluiceways and hydromechanical gates, as well as post tensioned anchors, a walkway and civil work on the embankment.

The dam was also equipped with a new safety boom and public safety panels.

ECS completed the procurement review, acted as the Project Manager and supervised the work carried out by Limoges. ECS was responsible for the project schedule, quality control processes as well as helping with logisitcs, technical questions and update meetings.

ECS was also responsible for the coordination for the various communications and requirements involving the different stakeholders involved in the project.

CLIENT

Saint-Colomban via Limoges et fils

LOCATION

Saint-Colomban, QC

DATE

September 2023 to April 2024

Team

COST

1 400 000$

PROFESSIONAL FEES

85 000$

Services Provided

  • Project and Construction Management
  • Fulltime site supervision
  • Management of logistics, changes et needs of various stakeholders
  • Coordinating the work with the contractor
  • Responsible for quality control and qualit assurance
  • Responsible for aligning all stakeholders
  • Responsible for organizing the schedule and timelines

Challenges

  • Work was near a watercourse which needed additionnal protection during the project
  • Constant communication with local residents
  • Short timeline before the winter months

Digital Twin